NEWFOUNDLAND DEVELOPMENT

“The service provided by Freeform3d was excellent. They integrated well with both our temporary works and construction teams, providing a focused yet flexible approach within a demanding timescale.”

 Jenni MacGregor, Head of Planning, BAM Nuttall Ltd

The model developed with the team at Newfoundland included a detailed top down construction sequence and colour-coding of internal finishes and MEP works.

The model was used to develop both the detailed sequence of the top-down excavation and the tower crane strategy. Both were reviewed and refined using the model to test the programme over a two month development.

The basement levels were exploded out using Synchro’s advanced move-tools to allow for the sequence to be clearly articulated.

IMAGE FROM REAL-TIME WORKSHOP 4D MODEL

IMAGE FROM REAL-TIME WORKSHOP 4D MODEL

4D INTERNAL MODEL FILTERED SPLITSCREEN